This is regarded as a period of time where the baseline of activities should not be changed. It is the current period + the next reporting period
What is the freeze period?
This is formal proposal to modify the established Performance Measurement Baseline
What is a Baseline Change Request (BCR)?
These are reasons a BCR may be denied (name one)
•Change is Out of Scope
•Change would cover a legitimate variance
•Change retroactive or in the freeze period
•Not enough MR is available
This is a type of baseline change where planning packages are converted into work packages as work becomes near term.
What is a rolling-wave BCR?
This is a term used to refer to the process that tasks place when the BCWS (Budgeted Cost of Work Scheduled) is set equal to the BCWP (Budgeted Cost of Work Performed) earned to date.
What is S=P?
This document is updated after a BCR is approved and the change is implemented in the scheduling and cost systems
What is a Work Authorization Document (WAD)?
This baseline change covers things like Task Name Change updates, EVT updates, and updating attributes that do not affect the PMB, such as a CAM name change.
What is an administrative BCR?
These systems are updated when a BCR is approved
What are the scheduling and cost systems?
These situations are okay for a retroactive change to be made to the baseline (name one)
•Correction of errors.
•Customer approved adjustments for negotiated amounts or program restructuring.
•Accounting adjustments.