100

This is regarded as a period of time where the baseline of activities should not be changed. It is the current period + the next reporting period

What is the freeze period?

100

This is formal proposal to modify the established Performance Measurement Baseline

What is a Baseline Change Request (BCR)?

100

These are reasons a BCR may be denied (name one)

•Change is Out of Scope

•Change would cover a legitimate variance

•Change retroactive or in the freeze period

•Not enough MR is available

200

This is a type of baseline change where planning packages are converted into work packages as work becomes near term.

What is a rolling-wave BCR?

200

This is a term used to refer to the process that tasks place when the BCWS (Budgeted Cost of Work Scheduled) is set equal to the BCWP (Budgeted Cost of Work Performed) earned to date.

What is S=P?

200

This document is updated after a BCR is approved and the change is implemented in the scheduling and cost systems

What is a Work Authorization Document (WAD)?

300

This baseline change covers things like Task Name Change updates, EVT updates, and updating attributes that do not affect the PMB, such as a CAM name change.

What is an administrative BCR?

300

These systems are updated when a BCR is approved

What are the scheduling and cost systems?

300

These situations are okay for a retroactive change to be made to the baseline (name one)

•Correction of errors.

•Customer approved adjustments for negotiated amounts or program restructuring.

•Accounting adjustments.