How often the SOV tracker should be submitted.

What is "weekly?"

Also acceptable: What is "every Friday, sometimes every Saturday?"

100

The color the SOV tracker turns should quantity installed exceed quantity awarded.

What is "red?"

100

Compensation of the local construction subcontractor for a line item before it is complete.

What is "partial payment?"

100

In a perfect world, you would proceed with a new line item on the SOV after the price has been proposed, agreed upon and added to the SOV; however, at a minimum, this should be done prior to proceeding with a new line item, NOT AFTER.

What is "agree upon the price?"

100

The country in which this bathroom was refurbished.

What is "Thailand?"

200

A fast and easy way to measure cable length installed.

What is "read the cable length noted on each end and calculate the delta?"

200

A type of LCS submittal that will not get paid should quantities appearing on it exceed the quantities allotted in the subcontract.

What is "invoice?"

200

Where you can refer to see if a line item is allowed to be partially paid.

What is "the line item header within the Schedule of Values."

200

This should be done as often as possible during the course of construction to add new line items and adjust the quantities of existing line items as needed, rather than wait until the end.

What is "modify the subcontract?"

200

The proper name for a Russian Nesting Doll

What is a "Matryoshka?"

300

What to do if Tech2 Solutions and the local construction subcontractor do not agree on quantities of line items completed.

What is "walk the site together?"
300

An alternative way, besides adding a new line item, to address the additional cost to the LCS for trenching through thicker than expected hard surface.

What is "add quantity to the trenching through hard surface line item?"

300

The construction industry typically requires a down payment, and less solvent construction subcontractors ask for up front payment, which we do not do when the project is funded by the U.S. Government. They must provide something in return for payment. To work within this constraint, payment can be made for these, which have to be provided and approved regardless, before construction commences.

What are "submittals?"

Also acceptable: What are "mobilization costs, like QA and EHS Plan Training?"

Also acceptable: What is "insurance?"

300

This happens when you have a subcontractor proceed with a new line item that has not been approved, and, ideally, included in a subcontract modification

What is "a ratification?"