SDOP
ARCOS
SUBSTATION SWITCHING
OVERHEAD SWITCHING
UNDERGROUND SWITCHING
100

Define EWP. 

Permission to work on or in close proximity to energized lines or equipment above 600 V, for which the source of supply could automatically re-energize the lines and equipment are disabled.

100
What does ARCOS stand for?

Automated Roster Call Out System

100

What is required in a switching order?

Purpose of switching

Date

Name of person issuing switching

Name of person executing switching

Start time (no completion time)

Numbered steps

100

Name considerations for switching.

Voltage Regulations

Schemes 

Wire size

Function switches

Key/Cent customers affected

Load

100

What is LTD?

Location - Term - Destination

200

Name conditions that limit you from issuing an EWP.

  • Ground protection disabled 

  • Reclosing disabled 

  • Trip coil monitor alarm 

  • Battery alarm 

  • Relay diagnostic alarm 

  • Low SF6 alarm 

  • Bad weather 

  • Scheduled switching for that breaker/device 

200

When would you need to ARCOS a crew?

When 3 or more crew members are needed.  

At night when staffing is low

When there is an injury/emergency

During storms/major damage

200

What is the purpose of a distribution station breaker?

Designed to break load and protect transmission lines from fault 

Cannot get clearance on breaker by itself, no visible air gaps 

Designed to open/close under normal and abnormal conditions 

Designed to carry normal load without overheating 

Designed to open quickly for faulted circuits without damaging itself or other equipment 

200

What considerations would you take when operating a solid blade switch?

Disable reclosing on most upstream device looking in normal direction

Consideration disable ground protection if load will trip ground

200

What is the leap frog method for isolating an UG fault?

Red go ahead, black go back

Open/tag as you go

300

Define a clearance. 

Permission to work on a line section, bus or apparatus that is disconnected from all sources of electrical energy by having disconnect switches or other appropriate visible air gaps open, made inoperable where possible and properly tagged.  

300

Who would you contact before ARCOSing a crew?

Supervisor on call (SOC) or first responder on call for outside regions

300

Name the different types of differential scheme and how you identify the zone of protection. 

Bus/Bank Differential 

High side is AIM switch but no Low-Side bank breaker 

Bank differential that looks all the way out to end of distribution lines 

Zone of protection overlaps with PCB Breaker overcurrent protection 

Bank and Bus Differential  

Differential scheme has both AIM switch on high-side and Low-Side bank breaker  

Both have CT's that overlap each other 

Bus Differential 

High-side fuse and Low-side bank breaker 

Low-side bank breaker has CT's for differential scheme 

Overlaps with CT's on feeder breakers 

No high-side differential  

300

Why would you want to make double loops in OH switching?

When dealing with 1/0 wire that would otherwise burn up if we tied circuits through it.  

300

What is the most common type of wire used for UG?

1/0 AXNJ 

400

If a voltage regulator is on lower 10, does it have more or less carrying capacity?

Less--as a voltage regulator moves further from neutral, it has less carrying capacity. 

400

What is the J/A rule?

Journeyman/Apprentice Rule

Requires that each apprentice have a journeyman riding with them.  Only the SOC can uncheck this box

400

What steps would to take to bypass a breaker with a direct bypass and regulators?

Disable reclosing

Place regs to MNO

Disable ground

Close bypass

Open 3 switch

Tag 3 switch

Open breaker

Open 1 switch

Tag 1 switch

400

When tying two circuits with different substations and both feeders have LTCs, what do you need to consider in regards to regulation? 

Place one LTC to manual, usually the larger of the two so you have control over the larger piece of equipment. 

400

If you are switching through an auto cubicle, what switching steps should you take?

Place cubicle to MANUAL

If used for clearance, put to local

Open

Lock open

Tag

500

Can you have two or more crews on a clearance at one time?  Why?

Yes--they are hold multiple clearances within the same parameters but each crew needs their own set of grounds for their individual work locations. 

500

What information is needed for an ARCOS call out?

TCMS reference number

Address of work location

Description of work being performed/trouble

# of crew members needed

500

What steps would you take to transfer load from one breaker to another with same bank/same bus and both feeders have regulators?

Disable R on both feeders

Place both sets of regs to MNO

Disable G on feeder being taken out

Close 1 transfer switch to test best

Disable G on feeder that will carry load

Close other transfer switch to tie

Open 3 switch

Tag 3 switch

Open breaker

Open 1 switch

Tag 1 switch

Put good breaker back in service (G, ON/AUTO, R)

SC on breaker being taken out

500

If you have a breaker lockout, what do you do?

Check SCADA breaker for targets/fault data/alarms

Review TCMS calls to find details for outage

Send out lockout page

Check schemes to see if they operated/isolated fault

Check SCADA devices to try and isolate fault by remote

500

When executing emergency UG switching, do you isolate mainline or 1/0 first?

mainline then 1/0