                            True or False
If an item is not included on the original punch list, it is exempt from being completed by any constructor or subcontract.
                            What is False.
If the item needs to be adjusted, replaced, fixed or installed, whether on the punch list or not, it is required to be completed (per AIA A201-General Conditions of the Contract).