Construction Quality Management
Plans and Specs
Project Administration
Inspection Plans
Random
100

These are the two organizations that make up the Construction Quality Control Management program.

Who is the Contractor's Quality Control System(QC) and the Government's Quality Assurance System(QA)?

100

This type of plan shows contours, boundaries, roads, utilities, trees, structures, references, and any other significant physical features.

What is Site plan?

100

The NCF coordinates with what organization for design/specifications, construction estimates, and bill of materials preparation.

Who is Naval Facilities Engineering Systems Command (NAVFAC)

100

This document is initiated and prepared by the project supervisor, with details on procedures, instructions, and reports during the entirety of the project. 

What is the Quality Control (QC) Plan?

100

This is the amount of workdays in advance that the project supervisor schedules the preparatory phase meeting and notifies attendees. 

What is 3 days?

200

This organization's policy dictates that the quality of construction projects shall be properly managed to assure that project requirements are being met. 

Who is Naval Facilities Engineering Command(NAVFAC)?

200

This type of drawing provides information to manufacture a machine part or erect a structure.

What is Working?

200

This is the amount of time the Naval Construction Force(NCF) call for work process is conducted.

What is 24-month rolling cycle?

200

This drawing must be 100 percent complete and must also reflect the responses to previous review comments. 

What is pre-final submittals?

200

At what construction level is the Level III Gantt chart the primary management tool.

What is Project Level Tasking?

300

This individual is responsible for conducting the periodic Quality Control meeting. 

Who is Unit quality control manager?

300

This document defines and limits a project's material, its fabrication, and its processes and procedures, based on the intent of the engineer or designer. 

What is Specifications?

300

This individual conducts mission analysis and begins task organization and table of organization (T/O) assignment upon receipt of the construction directive.

Who is the Operations officer?

300

This type of submittal describes the complete extent of the work in the preliminary manner.

What is the design development submittal?

300

This is known as the backbone of the QC System.

What is the Three Phases of Control?

400

This is the primary focus of the quality control system.

What is prevention?

400

This type of drawing reflects minor changes or field adjustments made to official contract drawings while in the field during construction.

What is Re-Line Drawings?

400

This element is responsible for schedule coordination and resource assignment. 

Who is the support element?

400

This is addressed in the safety plan.

What is the safety and occupational health requirements?

400

The QC Manager implements and manages the QC System and is directly responsible to whom.

Who is the commanding officer?

500

This individual is responsible for inspecting all material and equipment received, to ensure that it complies with the contract. 

Who is QC manager?

500

This type of drawing is 100 percent complete and used in the bidding process but must be signed by the contracting officer. 

What is Final Drawings?

500

During the initial project planning, higher headquarters, in conjunction with NAVFAC , conducts design reviews, initial estimates and _____________ for initial employment planning. 

What is constructability review?

500

This is provided in the activity hazard analysis(AHA).

What is detailed identification of project-specific hazards and controls?

500

These are the two broad categories of task organization the Naval Construction Force(NCF) uses for mission accomplishments.

What is general engineering and defensive operations and tactics?