100

These threshold of hours and/or dollars spent triggers a project to fall under the SDLC

What is 1,000 hour and/ or $500,000

100

Name the 3 different classifications used for documentation of artifacts and documents

What is Mandatory, Conditional, and Evolving

100

The Quality Assurance (QA) Test Lead is responsible for this

What is creating a set of test scenarios to validate the expected system functionality and meets overall test objectives

100

Where can the project manager find a more specific criteria and methodology to complete this deliverable is outlined on this page

What is the Strategic Sourcing Page

100

Project Manager's are responsible for submitting all contracts no matter the cost to this person

Who is Reina Albanez - Reina.Albanez@jetblue.com

200

During the Closure Phase how many days from deployment does the Hypercare Defect Log has to be sent out into ServiceNow? As what type of ticket?

What is 30 days/ as a Problem ticket

200

The report that the final document produced for the project used to assess the success of the project called

What is the Project Closure and Lessons Learned Report

200

These 2 people are responsible for initiating the go-live approval checklist which is located in ServiceNow

Who is The Scrum Master and/ or Project Manager

200

Name 2 of the Conditional Deliverables

What are 

Business Continuity Plan 

Technical Recovery Procedures 

Transition Plan 

Business Process Documentation

200

Both the mandatory deliverables of __________ and _________ are considered evolving documents

What are the Project Overview and Business Case