Time management processes
Diagramming, dependencies
Estimations
Critical Path, Floats
Supergame
100

Define activities process is a part of what process group?

Planning

100

What is PDM?

Precedence Diagramming Method

100

What is the difference between analogs and top-down estimating?

no difference

100

What is the predecessor to "Sequence Activities?

Define activities

100

How many processes are in Time management?

7

200

What process is the processor to Develop Schedule process?

Estimate activity durations

200

What is the logic of Start-to-Finish relationship?

Activity A must start before Activity B can finish

200

An information gathering technique used as a way to reach a consensus of experts on a subject. What this is about?

Delphi Technique

200

What is the critical path?

critical path is the longest path in your project's schedule network diagram, and is the SHORTEST possible duration for the project

300

How many processes from Time Management are part of the Planning process group?

6

300

What is an external dependency?

The external dependency is defined as the relationship between project activities and non-project activities.

300

What does heuristic mean?

Generally accepted rule or best practice

300

What is a Free float?

the amount of time that a task can be delayed without impacting the subsequent task.

400

What is the most complicated process in Time management?

Develop Schedule

400

Lead is an acceleration of the successor activity and can be used only ...?

on finish-to-start activity relationships

400

The technique to schedule activities within a given project is represented by the use of arrows. What is this?

arrow diagramming method (ADM)

400

When a task has a positive float number, it is considered part of the non-critical path. Is it true?

Yes, it is.