Define activities process is a part of what process group?
Planning
What is PDM?
Precedence Diagramming Method
What is the difference between analogs and top-down estimating?
no difference
What is the predecessor to "Sequence Activities?
Define activities
How many processes are in Time management?
7
What process is the processor to Develop Schedule process?
Estimate activity durations
What is the logic of Start-to-Finish relationship?
Activity A must start before Activity B can finish
An information gathering technique used as a way to reach a consensus of experts on a subject. What this is about?
Delphi Technique
What is the critical path?
critical path is the longest path in your project's schedule network diagram, and is the SHORTEST possible duration for the project
How many processes from Time Management are part of the Planning process group?
6
What is an external dependency?
The external dependency is defined as the relationship between project activities and non-project activities.
What does heuristic mean?
Generally accepted rule or best practice
What is a Free float?
the amount of time that a task can be delayed without impacting the subsequent task.
What is the most complicated process in Time management?
Develop Schedule
Lead is an acceleration of the successor activity and can be used only ...?
on finish-to-start activity relationships
The technique to schedule activities within a given project is represented by the use of arrows. What is this?
arrow diagramming method (ADM)
When a task has a positive float number, it is considered part of the non-critical path. Is it true?
Yes, it is.