PSM 1
PHA
Emergency Response
PSM 2
MOC
100

What does PSM stand for?

What is Process Safety Management (PSM)?

100

What does PHA stand for?

What is Process Hazard Analysis?

100

This PSM element ensures coordination with local emergency response organizations.

What is Emergency Planning and Response?

100

PSSR

What is Pre-Start Up Safety Review (PSSR)?

100

MOC

What is Management of Change?

200

This is the minimum number of elements required in a Process Safety Management program according to OSHA.

What is 14?

200

Employees with experience and knowledge specific to a process

What are (who are) qualified PHA Team Members?

200

Team members from each operating unit that are trained in Emergency Response?

What is the Fire Brigade?

200

This PSM element ensures that critical process equipment remains in good working order.

What is Mechanical Integrity?

200

Primarily responsible for developing and stewarding the MOC from concept through close-out

What is the MOC Originator?

300

PSI

What is Process safety Information?

300

PHAs must be updated and revalidated at this frequency.

What is every 5 years?

300

Who is responsible for reporting emergencies immediately upon discovery.

What is all Memphis Site Personnel?

300

Ensure employees are involved in the development and implementation of PSM.

What is Employee Participation?

300

Before a change is made, this type of review must be conducted to assess its impact on safety.

What is hazard analysis or risk assessment?

400

Name (3) of the 14 elements in OSHA's PSM program?

What is Employee Participation, Process Safety Information, Process Hazard Analysis, PSM Procedure Program, PSM Training Program, Contractors, PreStartup Safety Review, Mechanical Integrity, Hot Work Permit, Management of Change, Incident Investigations, Emergency Planning and Response, Compliance Audits, Trade Secrets?

400

Hazop

What is a Hazard and Operability Study?

400

This procedure requires you to badge in at closest assembly point.

What is a headcount procedure?

400

Includes information on the hazards of highly hazardous chemicals used or produced, information on the technology of the process, Information on the equipment in the process.

What is Process Safety Information (PSI)?

400

After changes are made to a piece of equipment or process, what must be completed prior to start-up?

What is a Pre-Start Up Safety Review (PSSR)?

500

What is the frequency of refresher training and compliance auditing?

What is every 3 years

500

Being on a PHA team or writing work instructions for a process

What are examples of employee participation?

500

Only when this occurs can you resume work on site.

What is The All Clear?

500

This PSM element requires that employees involved in operating a process be provided with initial and refresher training.

What is Training?

500

This role or person ensures the technical basis is sufficient, risk assessment is thorough and complete and action items have been identified and assigned for the MOC

What is the MOC Approver?