Number of calls and emails are needed before closing as unresponsive.
3
every call should have a follow-up email- after 2 calls and emails, the adjuster should be notified the ctr is unresponsive and a deadline email sent to the contractor on the third day of no response and closed on the 4th day.
Tandem Axle Dump Trailer can hold this much debris
1.67 tons- similar to a 4-5yard dumpster
You can print a scope without opening the entire scope in Xactimate- True or False
True- If you don't know how I can teach you.
Fuel Surcharge isn't standard- why?
Fuel cost is incorporated into the line items.
This was intended as a temporary solution during COVID as the fuel cost were rising at an unprecedented rate.
Required PPD for Category 2, Class 2
CF= 13,734.88
274.69PPD
Who do we request photos from
Contractor and Adjuster-if we need photos we need to also let the adjuster know so that they have a chance to send them or direct the ctr to send.
Single axle dump truck holds this much debris
2 tons- Dump truck typically has a 5 to 6 yard capacity.
Undermount sink removal includes this.
The sink and p-trap
Thermal Imaging- why is it not a customary item?
Thermal imaging detects temperature changes not moisture and many things can contribute to temperature changes. Best practices would still require moisture readings with a moisture meter.
A large dehu can handle what PPD?
70-109
Adjuster needs updated how often?
every 5 days
Good moisture readings include these
- Drying goal- taken from an unaffected area within the loss site.
- What material was the moisture reading taken from
- Type of meter used ( different types are for different materials)
Sink detach includes this.
Faucet-
Why don't they need a supervisor?
All technicians on site should be certified and able to complete all tasks without direct supervision.
Rare occasions this can be confirmed but this is rare- we would want to try to include a small amount of additional tech labor, if it is reasonable. It shouldn't be a typical thing we are confirming on our comparatives.
Required PPD for Category 3, Class 1
CF= 14,907.51
149.08
Submersible pumps can pump out how many gallons of water per hour
between 3,000 and 4,800 gallons per hour
Typically seen in crawlspaces or basements- not very common
This equipment is charged per hour so it's important to do the math. The calculation is also shown in Xactimate
Calculate gallons: depth in inches * 0.6235 * SF of area
This equipment is based on CFM not PPD to determine what size is needed.
Air Scrubbers
Desiccant Dehumidifier- this is because they work by a chemical reaction to draw the moisture from the air.
Class 1- 1 ACH
Class 2- 2 ACH
Class 3 and 4 - 3 ACH
Wood floor drying mat system can handle how many SF per unit?
100-400 of floor surface per unit- this item is not per mat but per unit in Xact. (including blower, hoses, mats, etc.).
Why isn't O&P standard for mitigation, content, specialty services, etc.
O&P is designed for use by general contractors when 3 or more trades are being performed. This is because there may be unforeseen costs the contractor may face. Mitigation services do not contain 3 or more trades and ALL associated costs are included in the Xactimate line items.
cfm 1,045.96 would require how many air scrubbers?
1 Large unit- handles up to 1,399CFM
2 Standard units- each handles up to 599CFM
This is where we can find the total amount of labor hours included in the line items on scope of work.
Labor Summary- this is beneficial when the ctr is requesting additional labor. We can pull this up and explain to the ctr exactly how much labor is included.
HEPA sandwich includes this- this is common on mold and abatements.
HEPA Vac
Agitated Scrub
HEPA Vac
90LF is what is covered by this drying equipment
Wall cavity injection dry- Blower, tubing, manifold, injectors, air mover (if used as part of the system), and all accessories for up to 90 lf of walls.
Ctr says they need a bigger dehu than ppd supports- "cause it helps dry quicker"
Is this true or false
False- as too much dehumidification can cause damages to the materials.
Required PPD for Category 1, Class 4
CF=12,698
317.45