Preparation
Grout
Underdrain Block
Installation
Commissioning
100

The first thing completed on the underdrain when onsite

What is a complete inventory to ensure quantity and good quality?

100

The type of cement required for underdrain installation

What is Portland Type II?

100

The inspection required after bell/spigot assembly

What is O-ring inspection?

100

Sealant required for end cap assembly

What is Sikaflex 1a or 11FC?

100

Prior to testing the filter this is required

What is a full inspection for proper installation?

200

Evaluation of the filter basin elevation is checked to determine

What is to determine the high point of the filter floor?

200

The acceptable max time before grout pours

What is 24 hours?

200

The tolerance underdrain laterals must be installed

What is +/- 1/8"?

200

The % anchor rods are to be inspected around flume

What is 100%?

200

Air distribution testing is completed to

What is ensure evenness of performance?

300

The correct filter floor surface roughness

What is 1/8" broom finish?

300

The temperature range grout can be installed

What is 40 F - 100 F?

300

The inspection required with IMS cap

What is inspect for all screws?

300

The required anchor rod depth

What is 5"?

300

Full rate backwash testing is performed to

What is to ensure integrity of installation?

400

Filter floor or wall coatings at the underdrain

What is not allowed?

400

The type of sand mixed with cement

What is clean dry masonry sand?

400

The tolerance a filter must be installed (between laterals)

What is +/- 1/4"?

400

The dimension grout chamfers are to be installed on underdrain

What is 2"?

400

Required after testing but before media loading

What is drain the water and reinspect the filter installation?

500

Before installing underdrain the filter piping and flumes must be

What is inspected and cleaned?

500

The proper sand cement  mix ratio

What is 2:1?

500

The elevation of fill grout or mono pours

What is to the top deck of the underdrain but not over the bell/spigot joint?

500

The anchor rod pull testing procedure

What is 3,200 lbs. of tension in 1,600 lb. increments?

500

Required after filter installation and testing

What is completed field service report (including pictures)?