Commissioning lead
Megan Mcgregor
Requisition submissions
Oracle
How many days into a given month does a project's cash flow forecast need to be updated?
Business day 10.
Form that details a building's equipment.
CMMS Asset Management Form
BAR
Building Access Request
Communications lead
Jody Decker
Invoice and PO look up
VMO Dashboard
When does the project baseline schedule need to be established?
After Gate 2.
Name 3 Vanguard buildings in Arizona.
Windsor
Wellington
Raintree
CSOC
Cyber Security Operations Center
Food Service Provider
Flik
Floor Plan, BAR, and Maintenance Request Submission
PlanOn
Name 3 unique items that get DocuSigned for a project.
CPAs
PCRs
Design Reviews
RFPs
Project Plan
Name 3 of Vanguard's former CEOs
Buckley
McNabb
Brennan
Bogle
MOP
Method of Procedure
Name 3 buildings that make up 80 Acres.
Bonus: which of the 3 was the last to receive a Pharos renovation?
Alexander
Leander
Theseus
Tech Requests
ServiceNow
Name the milestone for all four Gate reviews.
Gate 0 = Project Initiation
Gate 1 = Programming
Gate 2 = Design / Procurement
Gate 3 = Construction Completion
Gate 4 = Closeout
Which Vanguard building was constructed in 2018?
Neptune
CAMP
Capital Asset Management Program
Name 2 buildings that include a CDF.
Bogle
Orion
Library for existing drawings and drawing updates.
CAD Library
Project funding threshold for board level approval.
$35,000,000