Financing and Disputes
Protests, Disputes, and appeals
Modifications
100

Performance-based payments shall be used only:

When the contracting officer and the offeror are able to agree on the performance-based terms, the contract is a fixed-type contract, and the contract does not provide for progress payments.

100

Does a $75,000 claim resulting from a reduction of $350,000 and an increase of $275,000 require certification?

Yes, because the aggregate value of the claim exceeds $100,000.

100

Supplemental agreements are used to

definitize letter contracts.

200

customary progress payments percentages for Large and Small businesses

Customary progress payment rate is 80 percent 85 percent for small business concerns).

200

Protests may be filed with

the agency, the GAO, or the U.S. Court of Claims.

200

"Effective date" means the following

For a solicitation amendment, change order, or administrative change, it is the issue date.

300

What is the alternate dispute resolution (ADR)?

Procedures voluntarily used to resolve issues in controversy.

300

Who can authorize continued performance in the face of a protest after award?

the head of the contracting activity

300

Change orders issued under the "Changes" clause of the contract shall use which form?

SF30

400

The government's policy is to try to resolve all contractual issues in controversy by:

mutual agreement at the contracting officer's level.

400

The contracting officer shall consider all protests and seek legal advice

whether protests are submitted before or after award and whether filed directly with the Government Accountability Office, the U.S. Court of Claims, or the agency.

400

Unilateral modifications are NOT used to do which of the following?

Reflect other agreements of the parties modifine the contract terms

500

After receiving the GAO's written notice that a protest has been filed, an agency must give notice:

of the protest to the contractor or all parties who appear to have a reasonable prospect of receiving award.

500

 A protest based upon improprieties in a solicitation must be filed before bid opening or the closing date for receipt of proposals. In all other cases, protests must be filed

within 10 calendar days of the time the protester knew or should have

500

What is a bilateral mod and unilateral mod?

Bilateral means signed by both parties. Unilateral means signed by only the contracting officer.