It is each site recognizing their stake in the others' performance.
What is One Fleet Focus?
100
12 feet is the average length of this critical compnent that exists in both BWRs and PWRs
What is length of a fuel rod?
200
2012
What is the year XE WIN was formed?
200
Number of estimated hours to refuel.
What is estimated to take 58 hours?
200
Number of estimated hours it takes to refuel
What is estimated to take 94 hours?
200
Corrective Action Program & Behaviors, Engineering, Refueling Outages, Regulatory Performance, Work Management, and Workforce Planning/Development
What are the 6 focus areas in 2015?
200
99 Nuclear Power Reactors
What is the # of licensed Nuclear plants in the US today?
300
7000 women and men who work in Nuclear/Radiation related fields around the country.
What is the size of U.S. WIN network?
300
Decay Heat Removal
What is DHR?
400
XE WIN Corporate Sponsor
Who is Aziz Khanifar?
400
31 work orders executed (average)
What is the #of work orders executed per day?
400
38 work order executed (average)
What is the # of work orders executed per day?
400
Implement DHR hardening using the USA project at both sites; Design a critical path for optimal 30-day standard refueling outage; Implement processes necessary to reduce outage scope growth to less than 5 percent.
What are Refueling Outage Focus Area's 3 high level actions?
400
Shippingport Reactor (PWR) in Pennsylvania
Where was the first nuclear power plant in the US?
500
Membership includes: Minnesota, Iowa, Wisconsin, Illinois, Indiana, Michigan, and Ohio
What is Region III?
500
14 days during 2014 Fall outage
How many days from post refuel to generator close?
500
14.5 days for 2015 Spring Outage
How many days from post refuel to generator close?
500
-Lack of 30/30 ownership and commitment
-Milestone readiness
-Execution discipline
-Safety focus on shut down cooling
-Work window closure
-Project planning and execution