NGCP
ECD 6 Project Inspection & Monitoring
CQWS: Civil Works
CQWS: Electrical Works
CQWS: Mechanical Works
10

What are the three core values of NGCP?

Integrity, Competence and Passion for Excellence

10

What refers to a written list of deficiencies of the project required to be corrected by the Contractor prior to acceptance of the completed works?

Punchlist

10

What does CQWS stand for?

Construction Quality and Workmanship Standards

10

What does SEIL stand for?

Site and Equipment Identification and Labeling

10

The piping material for the domestic water pumping system shall be galvanized iron Schedule _____.

Schedule 40

20

Fill in the blanks.

NGCP Vision

To build the _________ and maintain the best power utility practice in Southeast Asia, with the collective efforts of a world-class professional work force.

strongest power grid

20

What refers to a duly organized, legal and existing corporation or company contracted by NGCP for a specific purpose, and which can also be referred to as one of the parties of the contract?

Contractor

20

Which type of steel support structure has advantages primarily in terms of strength, stability, and ease of fabrication - Lattice type of tubular?

Tubular

20

True or False. Neutral Bushing must not be insulated.

False

NGCP-CW-06.01-1001.02-00: Neutral Bushing shall have one insulated copper bus bar.Copper busbar shall be reliably connected to the groundinggrid to at least two different sides. The neutral busbar shallbe identified in Black color

20

For Transformer Deluge Water Spray System, pipes to be exposed shall be applied and painted with one (1) coat of epoxy primer and top coat of epoxy paint. What color should its final coat be?

Red

30

Fill in the blanks.

NGCP MISSION

To contribute to the nation's social and economic development and ________________ by efficiently developing and adequately operating the power grid to provide reliable electricity transmission service.

satisfy our stakeholder's needs

30

What is the IMS Form No. of Daily Inspector's Report (DIR)?

FM-PE-ECD-06AA

30

_____________ and Installation Precision are the top two common findings during Joint Final Inspection in Substation Projects (Bulletin No. 2024-16).

Workmanship

30

What is the standard color of equipment grounding cable?

Green or Yellow-Green horizontal stripes

Equipment grounding must be directly connected to ground mat.

30

True or False. In fire hydrant piping system, pipes to be embedded shall be first painted with one (1) coat of epoxy primer and then wrapped with anti-corrosion material (jute sack) and final coat of coal tar.

FALSE. Pipes to be embedded shall be first painted with two (2) coats of epoxy primer and then wrapped with anti-corrosion material (jute sack) and final coat of coal tar.

40

NGCP Code of Conduct

What type of offense carries a penalty of suspension of eight (8) to 20 working days?

Moderate offense

40

In the new revised CPER form of ongoing projects, what is the relative weight of contractor's monthly submission under Part C. Compliance to Documentary Requirement?

5%

40

What is the required gravel size and gravel paving thickness?

Size must be between 12-31 mm and gravel paving thickness of 150mm (6in) (NGCP-CW-05.01-1024.01-00)

40

Electrical Works: What is the correct phase color coding?

ø A – Red, ø B – Yellow, ø C - Blue

40

An ____________ shall be installed between the equipment and the foundation.

Anti-vibration Damper or Rubber Pad

50

NGCP Code of Conduct

Insubordination, or willful disobedience or intentional refusal of the employee to perform a lawful or reasonable order of a superior, falls under what offense type of offense?

It is classified as MAJOR OFFENSE under Rule 1, Section 3.

50

When is the effectivity date of PM-PE-ECD-06?

December 1, 2023

50

All anchor bolts, nuts and washers, turnbuckles and tension bars shall have a strength of ASTM _________.

ASTM A307

50

What is the standard panel dimension (LxHxW)?

L: 800mm, H: 2200mm, W: 800mm

50

What is the clearance between the loop pipeline and the transformer body in a Transformer Deluge Water Spray System?

1000mm