The purpose of California's ITM project.
What is modernizing the DMV's system?
The year when the ITM project was approved.
What is 2006?
The source of funding for the DMV modernization project.
What is taxpayers?
DMV projected that 11 million of the current year allocation will remain unspent due to project termination and reflect as savings
What is DMV'S scope variance?
The year that the DMV sponsored the ITM project.
What is 2005?
The year when the DMV awarded a $76 million contract to Electronic Data Systems (EDS) to update the state’s driver license and vehicle registration systems.
What is 2007?
The entity that received the most funding out of the entire project budget.
What is Hewlett-Packard Enterprise Services (HPES)?
The results were negative 173 million of the cost variance
Was cost variance overbudgeted?
The length of time in which California did not update its DMV technology.
What is 40 years?
The year when the DMV issue a cure notice to the primary vendor, HPES, expressing serious concern regarding HPES’s ability to successfully complete the project.
What is 2012?
The total amount of funding spent from the budget of $208 million.
What is $135 million?
Schedule variance is negative 72 million from taking earned and subtracting planned value
Is the project behind schedule?
The amount of independent subprojects to improve the DMV's core system.
What is four independent subprojects?
The year when the project was terminated.
What is 2013?
The project's initial budget amount.
What is $242 million?
DMV new program named Fi$cal was expanded resulting in an increased budget (1.2 billion)
What is the planned variance in 2007 that hurt the company?
Name one of the four independent subprojects for improving the DMV’s core system.
What is...
update DMV’s database OR update DMV’s transaction management system OR build new web-based driver license and vehicle registration systems OR update DMV’s code written in a now-obsolete programming language?
The month and year that the project would have been implemented in the DMV.
What is May 2013?
The amount of money still owed to HPES at project termination.
What is $1.5 million?
High costs of certain projects and the failures of others continue to make the state’s oversight of information technology an area of high risk (termination)
What was the cause of a negative variance (Demise)