Your project has an EV of 600,000, SPI =1.23, CPI = 0.76. This value has been calculated to be 487,804.88.
What is the PV?
Tells what amount of money we plan to spend for the whole project.
What is BAC or Budget at Completion?
What is the Estimate At Completion?
EV - AC
BAC/CPI
What is EAC?
Your project has AC of $750,000 SPI = 0.68 CPI = 0.87. This value is calculated to be 959,558.82
What is the PV?
Tells us how far we are behind or ahead of schedule.
What is SV or Schedule Variance?
It is the cost we have to spend from this point to complete the project
What is the Estimate to Complete?
%Complete X Budget
What is Earned Value?
What is ETC?
Your project has a CV of -81,000, SPI of 1.19 and PV = 560,000. It is calculated to be 747,400.
What is the AC?
Tells what value we are getting for every dollar spent
What is Cost Performance Index? (CPI)
The amount that we are over or under budget as of today?
What is VAC or Variance at Completion?
EV - PV
What is SV?
BAC - EAC
What is VAC?
Your project has an SPI of 0.92, a CPI of 0.75. You have spent 400,000. You are in the third month of a six month project. What is 652,173.91?
What is the Budget at Completion? (BAC)
Indicates that a critical path activity took longer than planned because work is being done at 89% of the rate we planned.
What is the SPI?
EV / AC
What is CPI?
The project has an SV of -47,000 and a CPI of 1.02. The PV is 130,000. The project is 12 months in duration and it is the beginning of Month 4.
It is calculated to be 460,000.
What is the ETC?
Tells us whether we are over or under budget.
What is Cost Variance or CV?
What is The CV<?