Phased & Confused
"Monday, Monday"
"You down with SPP? Yeah you know me!"
Show Me the Money
"My Name is What?
My Name is Who?
My Name is….."
100

This initiates each phase of the new load interconnection process.

What is an application? 

100

This is the software platform where all action items and large load projects are tracked.

What is Monday.com?

100

SPP studies do not start until this phase.

What is Phase II?

100

The official launch date of implementation for Sunflower's Load Interconnection Process.

What is August 18?

100

This is the name of the group email address that should be included on all email correspondence for load interconnections involving Sunflower.

What is loadaddition@sunflower.net ?

200

The preliminary rate analysis is delivered in this phase.

What is Phase I?

200

This form is housed in Monday.com and is used as the mechanism to collect data from potential projects.

What is the Phase Applications?

200

This purely informational, non-binding request is submitted by Sunflower to SPP.

What is the informational AQ?

200

A project requires a fee schedule starting at this megawatt level.

What is 25 MW and above?

200

The initial screening analysis is performed by this SME.

Who is Ryan Yokley?

300

Called project development, this phase lasts four months to two years.

What is Phase III?

300

This is how I can expect to be notified I have been assigned a task to support this process.

What is An auto-generated email from Monday.com.?

300

SPP states that they will turn around all studies within this timeframe.

What is 90 days?

300

After each project phase, Sunflower will issue this for any outstanding study deposits.

What is An invoice?

300

The point of contact for all SPP studies is this SME.

Who is Nathan Pearce?

400

A one-line diagram and preliminary cost estimate are packaged together in this Phase II study.

What is the preliminary facility design study?

400

Every large load project in Monday.com will have this item to track progress between phases.

What is the Checklist?

400

If a transmission upgrade is needed to serve a specific load, but isn’t classified as a network upgrade through SPP, the cost responsibility falls entirely on this party.

What is The applicant?

400

To ensure timely service, this is required for all fees and deposits before any work begins in each project phase.

What is Payment in advance?

400

This SME ensures capacity for resource adequacy requirements when a sleeved PPA is not involved.

Who is Erica Schmidt or Corey Linville?

500

The introduction of the Member and Sunflower to the end-use consumer indicates you are ready to transition into this phase.

What is Phase III?

500

This is the dashboard that rolls up all the project information, phases, and location data, serving as the resource for project updates.

What is the Prospective Load Dashboard?

500

This is a pre-requisite to file the AQ through SPP.

What is a RESA?

500

This is the main difference between a study deposit and an application fee.

What is Refundable vs Non-refundable?

500

This is the mechanism that outlines the rates, standard terms and conditions for service between Member, Sunflower and load applicant.

What is The RESA?