This Earned Value technique assigns 0% performance until a task is fully completed, at which point it jumps to 100%.
What is a 0/100?
QBDs must be assigned for tasks that have a baseline duration that spans for equal or than this amount of reporting periods
3
Near term activities that consume resources that are planned in detail are called this.
What are Work Packages?
This technique assigns 50% performance when the task starts, but cannot gain any more until a task is fully completed, at which point it jumps to 100%.
What is a 50/50?
This Earned Value Technique is for support type activities and the percentage earned must always equal the duration % complete.
What is an LOE?
Activities that consume resources that are further out in the future and planned with less detail are called this.
What are Planning Packages
This Earned Value technique must be supported by a list of steps, or Quantifiable Backup Data, in order to evaluate how performance can be earned
What is a "% Complete"?
This document is a hierarchical breakdown of project's event, accomplishments, and criteria but does not include scheduling details like durations or dependency logic.
What is the Integrated Master Plan (IMP)?
This report, introduced in 2020, is a replacement for IPMR and is required for most new DoD Earned Value contracts.
What is the Integrated Program Management Data and Analysis Report (IPMDAR)?