The number of years since PWGS's last DART injury.
What is 4 years?
The height of the stacks.
What is 210 feet?
The block that was constructed first during the conversion to gas.
What is Block 2?
The percentage of ATC owned by WEC Energy Group.
What is 60%?
The regular inspection frequency for the environmental cover system.
What is annually?
The year of PWGS last lost time injury.
What is 2011?
The temperature the 20ST Reheat Turbine Inlet Temperature must be above to constitute a "hot start".
What is 500 oF?
The output of the coal plant.
What is 400 MW?
The generating capacity of WEC Energy Group assets to the nearest GW.
What is 8 GW? (Specifically 8.150 GW)
The percent opacity for visible emissions allowed by the air permit.
What is 20%
The height of a potential fall for which wall openings must be guarded.
What is four feet or more?
The rated steam turbine output.
What is 265 MW?
The year Block 1 went into commercial operation.
What is 2008?
The year that coal will be eliminated as an energy source for WEC Energy Group.
What is 2032?
The maximum design intake velocity required to comply with impingement mortality standards.
What is 0.5 feet per second?
The number of employees who can be attached to a vertical lifeline for appropriate fall protection.
What is one?
The two cycles which make a plant "combined cycle".
What are the Brayton and the Rankine Cycles?
The increase in the output for the plant following the conversion from coal to gas in orders of magnitude (i.e. 1X, 2X, 3X, etc.).
What is 3 orders of magnitude?
The potential max load required in GW by the Vantage Data Center in Port Washington.
What is 3.5 GW?
The maximum concentration in ppm of CO at 15% O2 for a 24-hour rolling average per the air permit.
What is 3.0 ppm?
The incident energy, in cal/cm2, at which arc rated clothing is required?
What is 2 cal/cm2?
If not maintained above this point, the gas turbine load at which duct burners will shutdown.
What is 90% of base load?
The year the plant was designated a National Historic Mechanical Engineering Landmark.
What is 1980?
The expected increase to the nearest GW of projected added electric demand from 2026-2030
What is 3 GW? (Exact answer is 3.4 GW)
The total NOx emissions in tons which may not be exceeded in any 12 consecutive month period.
What is 318.0 tons?