When a worker can visit job site and work
After safety orientation is complete
What it mean SWPPP and where is need it
Storm water pollution prevention plan; and shall be installed to prevent any chemical, like concrete ,diesel or any chemicals getting to a water body; creeks, bayou
Fire extinguisher types and how often required to be inspected and PASS means
Type A; for combustibles; Type B for Flammables; type C for Electrical and Type D for metallic fire; typical ABC ; Monthly (visual, pin, cylinder damages); Annual (state certify, re-load,etc)
Pull the pin, Aim the fire, squeeze, sweep
How you are handling materials
Use proper lifting /handling techniques and PSC protocols
pre-excavations process and permits; inspections
do assessment/ check list/ permit; call 811 locate underground utilities; CP inspect /evaluate before allowing entry; and 5' deep or more will need of a protective system
where can you smoke at open field site during working hours
Smoke in designated areas is permitted; away from equipment, flammables, combustibles, equipment
who keep all the SDS on the field
Mainly Supte, HSE, or work and tool trailer have available and access to any SDS from chemicals used
What we normally do when gas cylinders are not in use
Close the valves/ set cap, remove regulators and gauges and follow company's protocols
which respirator has to be use, and seal tests explain
Select an appropriate respirator to control the hazard; provide field test for negative and positive test
In PRCS who sign the permit, and steps before entry; people and equip. involved
PRCS means; permit required confined space; CP sign the permit before personnel entry; Physical and Atmosphere evaluation is required; shall keep monitoring during the task;
If is there not Dumpster available where can I leave construction trash & debris
Is not permitted to accumulate general trash/debris/dunnage in work areas
Where can we clean concrete trucks and pour any concrete debris
Shall be into concrete washout containments only
Typical PPE required on the job site; and when you are grinding, or cutting (440 stihl ); explain
hard hat, gloves, work shoes, ear plugs, glasses plus face shield while exposed to debris while cutting or grinding
hand tool recommendations and protect yourself
be sure has a guard moving or rotating parts; use proper grinding disc for grinder size /type (RPM)
What is right angle to set up an extension ladder; how to use it
Inspect for any damages; Angle is 4:1; face the ladder/ maintain 3 points of contact; do not carry materials; extend it 3 ft above landing area
What is frontline daily safety planning process knowing as
STAR or pre-job briefing
LDH, safe water act, TCEQ work under EPA
They are state offices to follow all EPA standards in order to prevent contaminations in water, air and soil
PFAS and its components
Personal Fall Arrest System; harness, lanyard, suspension trauma protection, SRL (yoyo)anchor point
what is required to be a spotter or flagger
Trained on duties /hazards/communication methods/ signals
Establish correct communication method between spotter and operator
Main info before lifting any load
Know the weight of load; use adequate rigging equip. ; inspect every rigging like synthetic sling, wire rope or chain have legible capacity tags; determine right hitch
It is the offices only ones empower to stop a unsafe task/ work
any worker has the stop work responsibility if unsafe action taking place
what it means SPCC plan or when I need it
Spill Prevention, Control, and Countermeasure (SPCC); implemented to prevent and control almost any oil or any chemical spills
OSHA's requirement as fall protection systems
PFAS, guardrail, ramp, cover holes, vertical and horizontal life line; descender for self rescue
Basic steps and requirements to drive company truck; 360; accidents while driving
Conduct 360 walk around prior start/ move vehicle & equipment; back alarm works; all occupants wear seat belt; avoid distracted driving, avoid mobile device use(cell)
how can you describe a lift plan for a crane
Daily inspection; knowing the weight of load; establish a communication between operator and rigger; set up swing radius; tag lines use to control the load; load not be suspended when is not attended; crane on stable/ level surface