The Design Process
Construction Process
Chap. 5 Desjours
Project Personnel
Miscellaneous Chap. 5??
100
Designates the Owners needs, goals & objectives of the facility or project
What is the Program
100
The 3 phases of a construction project
What are the following: Pre-Construction phase Construction phase Post-Construction phase
100
The dollar value a CM is required to pay, and is based on the value the Owner would lose, in the event their project/building is not available for the Owner to do what they do.
What are Liquidated Damages?
100
The jobsite quarterback; responsible for all jobsite activities; the Super calls all the shots (or makes all jobsite related decisions)
Who is the Jobsite Superintendent?
100
Typically describes the design & construction process
What is linear, with a systematic, comprehensive approach?
200
To determine of the project can be completed (does the Owner have enough resources, the site, other project aspects.......
What is the Project Feasibility?
200
Execute the construction contract, commence a pre-construction conference, submit pre-construction Submittals, and mobilize to the jobsite
What is the Pre-Construction phase
200
The process of identifying any problems or areas f concern that exist so that these problems can be factored into the decision making that takes place during all construction phases.....doing one's "homework", related to the Project.
What is the Due Diligence process?
200
New CM graduate on the jobsite
Who is the Field Engineer?
200
The 2 most difficult project processes for the PM & Super
What is the project start up, and the project close-out?
300
First phase of the design process; uses bubble diagrams, and other rough sketches to organize space relationships, project organization, circulation patterns & paths, and massing
What is the Schematic or Conceptual design phase?
300
Build the project; complete the required submittals process, submit regular applications for payment, respond to needs of Owner.
What is the Construction phase?
300
Optimize resources to achieve the greatest value for money being spent on the project......being more economical with time & money, but providing as good a solution for the design intent.
What is Value Engineering (or VE)?
300
Captain of the project team; very experienced in construction & management processes
Who is the Project Manager (PM)?
300
Setting up the project site, and getting ready to build
What is Mobilization?
400
Next design phase; includes application of scale; ceiling, roof & wall heights are considered; materials, equipment & systems are researched and selected; sometimes, value engineering & constructability reviews occur.
What is the Design Development phase?
400
Comply with the required date of substantial completion, and the Punchlist, process all contract close-out requirements, and submit final pay application
What is the Contract Closeout phase or process?
400
The minor list of project adjustments, repairs, items to be finished, and other items not complying with the required contract documents.
What is the punch list?
400
What are the 4 fundamental management tasks
What is the following: 1. Assemble the best possible team (good luck) 2. Develop overall project schedule(s), and stick to them 3. Set up (or use existing ) Cost Control systems 4. Establish a QA-QC plan (based on reference standards)
400
Includes the following activities: Setting up & securing the jobsite, field office & temp. storage facilities Organizing jobsite access & parking. Securing temporary utilities, water & telephone/wireless services. Establish jobsite mgt. systems, and safety processes. Obtain all requirement permits & other building permissions & requirements
What is Jobsite Mobilization?
500
The final design phase; includes drawings & specs; the procurement phase typically follows.
What are the Contract Documents?
500
Project record documents, O & M manuals, extra materials & commissioning requirements & reports.
What are Project Closeout requirements or closeout documents?
500
True or False If an item is not included on the original punch list, it is exempt from being completed by any constructor or subcontract.
What is False. If the item needs to be adjusted, replaced, fixed or installed, whether on the punch list or not, it is required to be completed (per AIA A201-General Conditions of the Contract).
500
CM temporary employee, still learning the ropes; still a part of a university CM (or related) academic program
What is a CM Intern?
500
When the Owner takes possession of the project, and can begin the move-in process; the possible Liquidated Damages are eliminated.
What is the Date of Substantial Completion?