What does PSM stand for?
Process Safety Management.
What color tag indicates a scaffold is fully compliant and safe for normal use?
Green Tag.
At what height is fall protection required in Construction (OSHA 1926)?
6 feet or more above a lower level.
At what depth must a means of egress such as a ladder, stairway, or ramp be provided in a trench?
When the excavation is more than 4 feet deep.
What document must be completed and signed by all crew members before employees begin work over or near water?
A Task Safety Analysis (TSA).
What does ESWC stand for?
Electrically Safe Work Condition.
What OSHA standard does this SOP support compliance with?
OSHA 29 CFR 1910.119 Process Safety Management.
At what height must scaffold platforms have complete guardrails and toe boards installed?
When the work platform is 4 feet or more above the ground or next lower level.
What are the four levels of the Hierarchy of Controls for fall hazards?
How far can an employee travel laterally in a trench to reach a ladder or other means of egress?
No more than 25 feet
When the danger of drowning exists, what must employees working over or near water be provided?
A U.S. Coast Guard-approved life jacket or buoyant work vest (PFD).
Who is permitted to work on electrical circuit parts or equipment that have not been de-energized?
Only Qualified Persons.
In a PSM-covered facility, who retains responsibility for the covered process and compliance with OSHA PSM requirements applicable to process operation, design, engineering, and maintenance?
The facility owner/operator.
What is the minimum width required for a scaffold platform under normal conditions?
18 inches wide.
What is the minimum strength required for an anchorage used in a personal fall arrest system?
5,000 pounds per employee attached.
How far must spoil piles, equipment, and traffic paths be kept from the edge of an excavation?
At least 2 feet from the edge.
Can employees work alone while performing work over or near water where a drowning hazard exists?
No. Employees are required to work in at least two-person teams and are not permitted to work alone.
What does GFCI stand for?
Ground-Fault Circuit Interrupter.
When must an incident investigation be initiated following a process safety incident?
As promptly as possible, but no later than 48 hours after the incident.
How many times the maximum intended load must a scaffold be capable of supporting without failure?
Four times the maximum intended load.
How often must all fall protection equipment be formally inspected and inventoried by a Competent Person?
At least quarterly.
What percentage of oxygen is considered the minimum safe level before precautions must be taken for atmospheric hazards?
19.5% oxygen. Precautions are required below this level.
What is the minimum length of line required to be attached to a ring buoy used for emergency rescue operations?
90 feet of buoyant heaving line.
What three electrical boundaries are Qualified Electricians required to understand?
Name three examples of routine and non-routine work authorization documents required under this procedure.
Hot Work Permit, Safe Work Permit, Confined Space Entry Permit, or Exception Procedure.
What is the minimum height that an access ladder must extend above the platform being accessed?
36 inches above the platform.
What is the maximum length allowed for a lanyard?
6 feet.
Under what two conditions is a protective system not required in an excavation?
What is the maximum allowable spacing between emergency ring buoys?
No more than 200 feet apart.
What minimum score must be achieved on the Qualified Electrical Training Class written test?
80% or better.
Without written authorization through approved MOC processes, employees may not perform what five types of field changes?
What action must be taken if an employee cannot use a Self-Retracting Lifeline (SRL) on a scaffold ladder that is 10 feet or higher?
A variance request must be submitted to Corporate Safety.
A scaffold ladder accesses a deck that is 12 feet above the working surface. What additional fall protection is required?
A Self-Retracting Lifeline (SRL) is required unless deemed infeasible by a Competent Person and approved through the variance process.
How often must a Competent Person inspect an excavation?
Before the start of work, as needed throughout the shift, and after every rainstorm or other hazard-increasing event.
What three pieces of lifesaving equipment must be immediately available when employees are working over or adjacent to water?
Name three items of insulating or protective equipment that may be required when working on or near energized parts.
What documentation must be reviewed during a job walk when working with de-energized or tagged systems?
The isolation list and/or P&IDs (Piping & Instrumentation Drawings)
A supported scaffold has a height-to-base-width ratio greater than 4:1. What additional protection is required?
The scaffold must be restrained from tipping by guying, tying, bracing, or equivalent means.
List four situations that require completion of a Fall Hazard Risk Assessment (FHRA) before work begins.
Name four items that must be included in employee excavation training.
List the first four actions the SOP describes when a person falls overboard.
An employee is working around energized electrical parts. What two personal items are specifically prohibited by the SOP?
Conductive jewelry such as rings and necklaces.
What are four methods that can be used to verify employee understanding of PSM training?
Name at least five of the eight responsibilities or capabilities of a Scaffold Competent Person.
What are the three conditions that require an employee to be retrained in fall protection?
Atmospheric testing is required in excavations over what depth when a hazardous atmosphere exists or may reasonably be expected?
More than 4 feet deep.
What special requirements apply to PFDs according to the SOP?
All PFDs must have an approved light and approved retro-reflective material installed.
Name four abilities a designated Electrical Competent Person must possess.
Name the five actions employees are prohibited from performing without written authorization and approved MOC processes.
At what scaffold height are engineered drawings required, and who must approve them?
Any scaffold over 125 feet high requires design drawings that must be approved and sealed by a Qualified Person (licensed professional engineer) and kept on site.
A worker is performing temporary, infrequent work on a low-slope roof more than 15 feet from the roof edge and no conventional fall protection is being used. What control must be implemented?
A Safety Monitor must be used to ensure employees do not come within 15 feet of the roof edge. The Safety Monitor's sole responsibility is monitoring the work.
A trench is sloped using the maximum allowable slope identified in the SOP. What is that slope ratio and angle?
1.5 horizontal to 1 vertical, which equals approximately 34 degrees measured from the horizontal.
A winch line is under tension. According to the SOP, what is the danger zone around the line?
Employees must stay out of the area within 15 degrees on either side of a line under tension and never stand in, on, over, or in line with the cable.
A piece of equipment must be operated near overhead power lines. What is the minimum clearance distance required for uninsulated lines less than 50 kV?
20 feet.